Manage Production Routings and Sequential Operations
Step-by-step definition of manufacturing routings, operation dependencies, setup timers, and work instructions.
1. Overview & Business Value#
This comprehensive operational guide details the architecture, business workflows, configuration parameters, and execution steps for Manage Production Routings and Sequential Operations within SmartERP.
Step-by-step definition of manufacturing routings, operation dependencies, setup timers, and work instructions.
{screenshot:production-routings-and-operations-overview-dashboard}
2. Prerequisites & Security Access Groups#
- Required Modules:
mrp, quality_control, smarterp_manufacturing_costing - Security Groups:
Manufacturing User(Technical ID:mrp.group_mrp_user)Manufacturing Administrator(Technical ID:mrp.group_mrp_manager)Quality Inspector(Technical ID:quality.group_quality_user)
- Master Data Dependencies: Bills of Materials (BoM), routing operations, work centers with machine/labor hourly rates, raw material stock, and inspection checkpoints.
3. Step-by-Step Configuration & Execution#
Step 1: Navigating to the Module Interface#
- Log into your SmartERP instance at
https://smarterp.et/odoo. - Open the main App Switcher (grid icon in the top-left corner).
- Select the Manufacturing app icon.
- From the top navigation bar, open Manufacturing → Operations → Manufacturing Orders / Work Orders; Quality → Quality Control.
{screenshot:production-routings-and-operations-app-switcher-navigation}
Step 2: Creating and Parameterizing Records#
- Click the New button in the top-left control panel.
- Complete the mandatory fields in the record form:
- Finished Product (Mandatory): Manufacturable item variant linked to an active Bill of Materials
- Quantity to Produce (Mandatory): Target production batch volume in standard unit of measure
- Bill of Materials (BoM) (Mandatory): Active engineering recipe defining component roll-ups and operation steps
- Scheduled Date (Mandatory): Target production execution date and shift allocation
- Configure optional operational parameters and localized tags as required:
- Work Center Routing (Optional): Specific shop floor machine or assembly station sequence
- Lot / Serial Number (Optional): Assigned traceability lot for finished goods batch tracking
- Analytic Cost Account (Optional): Cost absorption center for direct labor and utility overhead
- Click the Save icon in the control bar to commit the record.
{screenshot:production-routings-and-operations-record-creation-form}
Step 3: Validating and Processing Transactions#
- State Transitions: Execute operational state progression (Draft → Confirmed → In Production → Quality Gate Passed → Done → Cost Closed).
- Ledger & System Impact: Consumes raw materials from inventory (crediting stock valuation), absorbs labor/machine overhead, and debits finished goods inventory at actual cost.
- Audit Verification: Automated recording of author ID, timestamp, and immutable revision history.
{screenshot:production-routings-and-operations-transaction-processing-state}
Principles of Operational Routing#
A routing defines the sequence of operations required to transform raw materials into finished goods. In SmartERP, routings are embedded directly within the Bill of Materials under the Operations tab.
Each operation specifies:
- The target Work Center.
- The standard computation duration (Fixed time vs Duration based on units produced).
- Operator PDF work instructions or embedded video guides.
- In-process quality control gates.
Procedure: Adding Operations to a BoM#
- Open your active Bill of Materials (Manufacturing > Products > Bills of Materials).
- Switch to the Operations tab and click Add a line.
- Fill in the operation attributes:
- Operation:
Raw Coil Slitting. - Work Center:
Heavy Slitter Line 1. - Duration Computation: Select
Compute based on real timeorSet duration manually. - Default Duration:
45minutes per 1000 kg.
- Operation:
- In the Work Sheet tab:
- Attach the engineering drawing or standard operating procedure (SOP).
- In the Sequence column, define execution order:
- Sequence 10:
Slitting & Edge Trimming - Sequence 20:
Cold Roll Forming - Sequence 30:
Galvanizing Bath - Sequence 40:
Final Stamping & Bundling
- Sequence 10:
Sequential Dependencies#
By default, operations proceed sequentially. SmartERP prevents operation 20 from starting until operation 10 has recorded completed output quantities, preventing inventory discrepancies on the shop floor.
4. Advanced Configuration Points#
- Automated Actions & Scheduled Tasks (Crons):
MRP: Recalculate BoM standard costs(mrp.ir_cron_bom_cost_roll): Runs weekly to update standard costing from latest procurement purchase pricesQuality: Trigger periodic inspection alerts(quality.ir_cron_inspection_check): Runs daily to flag mandatory quality testing queuesWorkcenter: Update OEE statistics(mrp.ir_cron_workcenter_oee): Runs hourly to compute Overall Equipment Effectiveness metrics
- Custom Print Templates & Reports:
- Production Order Traveler & Pick List
- Shop Floor Work Order Execution Slip
- Quality Inspection Certificate & Non-Conformance Report
- Manufacturing Cost Analysis & Variance Ledger
- Multi-Company Rules: Record-level security isolation under Company 1 (
Ashewa Technology Solutions S.C.), preventing cross-company ledger leakage across parent and subsidiary legal entities.
5. Comprehensive Troubleshooting Matrix#
| Error Symptom / Exception | Probable Root Cause | Corrective Action / Resolution |
|---|---|---|
BoM Missing Error: No active Bill of Materials found | Product variant lacks a verified and confirmed BoM in the system. | Create and confirm an active BoM under Manufacturing → Products → Bills of Materials. |
Component Shortage Block: Insufficient stock | Raw material components have not been transferred to the shop floor location. | Execute an internal transfer from main warehouse to production staging location. |
Quality Gate Blocked: Mandatory test failed | Work order failed critical quality tolerance threshold. | Perform required corrective rework or request authorized Quality Manager override. |
Workcenter Capacity Overload | Scheduled production duration exceeds available work center shift capacity. | Adjust scheduled start dates or distribute load across alternative work centers. |