Record Daily Site Diaries, Plant Hours, and Weather Logs
Mandatory site diary documentation: heavy equipment operational hours, skilled/daily labor headcounts, and rainfall delays.
1. Overview & Business Value#
This comprehensive operational guide details the architecture, business workflows, configuration parameters, and execution steps for Record Daily Site Diaries, Plant Hours, and Weather Logs within SmartERP.
Mandatory site diary documentation: heavy equipment operational hours, skilled/daily labor headcounts, and rainfall delays.
{screenshot:daily-site-diaries-and-weather-logs-overview-dashboard}
2. Prerequisites & Security Access Groups#
- Required Modules:
project, smarterp_project_governance, hr_timesheet - Security Groups:
Project User(Technical ID:project.group_project_user)Project Administrator(Technical ID:project.group_project_manager)Timesheet Approver(Technical ID:hr_timesheet.group_hr_timesheet_approver)
- Master Data Dependencies: Project master records, milestone stages, work breakdown structures (WBS), bill of quantities (BoQ), and employee billing cost rates.
3. Step-by-Step Configuration & Execution#
Step 1: Navigating to the Module Interface#
- Log into your SmartERP instance at
https://smarterp.et/odoo. - Open the main App Switcher (grid icon in the top-left corner).
- Select the Projects app icon.
- From the top navigation bar, open Projects → Dashboard → My Tasks / All Projects; Timesheets → Timesheets.
{screenshot:daily-site-diaries-and-weather-logs-app-switcher-navigation}
Step 2: Creating and Parameterizing Records#
- Click the New button in the top-left control panel.
- Complete the mandatory fields in the record form:
- Project / Task Name (Mandatory): Descriptive title of work package or milestone deliverable
- Assigned Project Team (Mandatory): Lead project manager and operational contributors
- Planned Dates (Mandatory): Scheduled commencement and milestone completion deadlines
- Customer / Stakeholder (Mandatory): Client partner linked to project contract and invoicing terms
- Configure optional operational parameters and localized tags as required:
- Analytic Cost Center (Optional): Dedicated project accounting account for expenditure tracking
- Bill of Quantities (BoQ) Line (Optional): Specific contractual BoQ item code for construction tracking
- Milestone Billing Weight (Optional): Percentage of contract value tied to milestone acceptance
- Click the Save icon in the control bar to commit the record.
{screenshot:daily-site-diaries-and-weather-logs-record-creation-form}
Step 3: Validating and Processing Transactions#
- State Transitions: Execute operational state progression (New / Scoping → In Progress → Review / Testing → Completed → Archived).
- Ledger & System Impact: Timesheet confirmations and project purchases post direct expenditures to the project analytic account, enabling real-time cost vs. revenue margin analysis.
- Audit Verification: Automated recording of author ID, timestamp, and immutable revision history.
{screenshot:daily-site-diaries-and-weather-logs-transaction-processing-state}
Purpose of the Daily Site Diary#
Under Ethiopian FIDIC and MoWUD contract conditions, the Daily Site Diary (smarterp_construction_daily_labor) is a legally binding record admissible in contractual claims, dispute adjudication boards, and delay analysis.
Procedure: Submitting a Daily Site Report#
- Open Projects > Construction > Daily Site Diaries on the mobile tablet or desktop.
- Date & Weather:
- Record weather conditions across morning and afternoon shifts (e.g.,
Heavy Rain: 14:00 - 17:30 (3.5 hours site stoppage)).
- Record weather conditions across morning and afternoon shifts (e.g.,
- Plant & Heavy Equipment Deployment:
- Tower Crane 1:
7.5 hours operating, 0.5 hours idle. - Excavator CAT 320:
6.0 hours operating, 2.0 hours breakdown (hydraulic hose). - Concrete Batching Plant:
8.0 hours operating (120 m3 batched).
- Tower Crane 1:
- Labor Headcount:
- Skilled Labor: 14 Carpenters, 18 Masons, 12 Steel Fixers, 2 Electricians.
- Daily / Unskilled Labor: 65 Daily Workers (Wetetosh).
- Work Executed: Summary of sections poured, blockwork erected, or forms stripped.
- Click Submit Diary.
4. Advanced Configuration Points#
- Automated Actions & Scheduled Tasks (Crons):
Project: Flag overdue milestone deadlines(project.ir_cron_overdue_tasks): Runs daily to notify project managers of pending schedule delaysTimesheets: Send unsubmitted reminder alerts(hr_timesheet.ir_cron_timesheet_reminder): Runs weekly on Friday afternoon to remind team members
- Custom Print Templates & Reports:
- Project Status & Milestone Execution Scorecard
- Interim Payment Certificate (IPC) for Construction
- Project Timesheet & Resource Utilization Summary
- Earned Value Management (EVM) Financial Report
- Multi-Company Rules: Record-level security isolation under Company 1 (
Ashewa Technology Solutions S.C.), preventing cross-company ledger leakage across parent and subsidiary legal entities.
5. Comprehensive Troubleshooting Matrix#
| Error Symptom / Exception | Probable Root Cause | Corrective Action / Resolution |
|---|---|---|
Access Rights Error: Cannot view confidential task | User is not listed as a project follower or team member. | Add user to Project Privacy Settings or Collaborators tab. |
Validation Error: Timesheet date outside active stage | Attempting to log labor against a closed or cancelled milestone. | Select an active task stage or request reopening of the target work package. |
Billing Rate Error: Missing employee cost rate | Assigned employee lacks an hourly labor cost rate on their profile. | Configure the employee hourly cost rate under Human Resources → Employees → HR Settings. |